Showing All programmes, all workstreams, 27 Feb 2026 to 8 Jan 2027

Delivery confidence

59%

11 workstreams in scope

Scope delivered

87%

Actual against plan

Milestones on track

20

of 30 in range

Milestones at risk

10

At risk or off track

Open risks and issues

15

10 risks, 5 issues

Workstream status

Ledger MigrationA. WhitfieldIdentity and AccessP. NandraLanding ZoneD. FaulknerDetection and ResponseL. BoatengPayments IntegrationS. RahmanWorkload MigrationR. IyerThird Party AssuranceC. MullinsData and ReconciliationJ. OkaforNetwork and ConnectivityH. SorensenData Centre ExitT. AdeyemiDigital ChannelsM. Trevino

Milestone roadmap

30 milestones in range

Ledger Migration

Identity and Access

Landing Zone

Detection and Response

Payments Integration

Workload Migration

Third Party Assurance

Data and Reconciliation

Network and Connectivity

Data Centre Exit

Digital Channels

CompleteOn trackAt riskOff trackFeb 2026 to Jan 2027
  • Ledger data model signed off14 Mar
  • Landing zone accreditation23 Apr
  • Privileged access tooling live17 May
  • Parallel run environment live12 Jun
  • Critical supplier assessment7 Jul
  • Migration wave 1 complete12 Jul
  • Faster Payments gateway certified22 Jul
  • MFA rollout to all staff1 Aug

Delivery burn-up

Planned against actual

Risks and issues

15 items in scope
ItemTypeSeverityStatusOwnerRaised
App store review cycle may delay releaserisklowmonitoringM. Trevino12 Aug
Payments test environment unstable under loadissuehighopenS. Rahman10 Aug
Log ingestion costs exceeding forecastissuemediumopenL. Boateng7 Aug
Wave 2 application owners unavailable for cutoverissuecriticalopenR. Iyer4 Aug
Historic data quality below migration thresholdissuehighmitigatingJ. Okafor2 Aug
Two critical suppliers yet to return assurance packsrisklowmonitoringC. Mullins30 Jul
Circuit provisioning lead times doubledissuehighopenH. Sorensen27 Jul
SWIFT vendor resource unavailable until next quarterriskcriticalopenS. Rahman26 Jul
Parallel run window collides with year end freezeriskhighopenA. Whitfield19 Jul
Guardrail exceptions accumulating without reviewriskmediummonitoringD. Faulkner16 Jul
SOC analyst recruitment behind planriskhighmitigatingL. Boateng11 Jul
Dependency mapping incomplete for 40 workloadsriskcriticalopenR. Iyer4 Jul
Regulatory reporting scope not yet baselinedriskmediumopenJ. Okafor30 Jun
Legacy application cannot support MFAriskmediummitigatingP. Nandra22 Jun
Data centre lease penalty if exit slips past Q4riskcriticalmitigatingT. Adeyemi12 Jun